OPAL Reactor reached design power of 20MW for the first time toda
y
ROBINSON, Robert
rro at ansto.gov.au
Fri Nov 3 16:05:32 CST 2006
See ANSTO's press release on:
http://www.ansto.gov.au/info/press/2006/OPAL_at_20megawatts.pdf
<http://www.ansto.gov.au/info/press/2006/OPAL_at_20megawatts.pdf>
OPAL reactor glows at full power
At 11:45 this morning, ANSTO's OPAL research reactor reached its full
operating power of 20
Mega Watts for the first time as part of the reactor's commissioning
process, which is yet to be
completed.
"This is a milestone because it means that we are a step closer to the full
commissioning of the
reactor," said Dr Ian Smith, ANSTO Executive Director. "This is a very
exciting time and we are
confident that the success to date in the commissioning process will assure
we reach full
operation on the planned schedule and realise the science capabilities and
radiopharmaceutical
production capacity which OPAL will provide for Australia.
In commissioning, reactor components and systems are made operational and
verified to be in
accordance with design and performance criteria. Reaching 20 MW today is a
significant
milestone for the ANSTO,INVAP (the prime contractor)and the project team.
"The water in OPAL's pool vessel is now emitting the distinctive blue glow
of Cerenkov
radiation, characteristic of nuclear fission," said Dr Smith.
OPAL will be a major contributor to Australia's nuclear medicine needs for
the next 40 years,
and is designed and constructed to ensure effective protection against
radiological hazards for
workers, the community and the environment.
When OPAL is fully operational and delivering radioisotopes and neutron
beams to the
necessary requirements, the current reactor, HIFAR, will be shut down.
___________________________________________________________________________
For more information and to arrange interviews please contact:
ANSTO Media Adviser, Sharon Kelly (02) 9717 9575 or 0400 394 085
*ANSTO is the Australian Nuclear Science and Technology Organisation, the
country's national nuclear research and development
organisation and the centre of Australian nuclear expertise - over 70 per
cent of all radioisotopes used in Australian nuclear
medicine are made in ANSTO's reactor.
----------------------------------------------------------------------------
----------------
Robert A. Robinson
Head, The Bragg Institute, B87
Australian Nuclear Science and Technology Organisation
PMB 1, Menai NSW 2234
Australia
Tel: +61 (2) 9717 9204
FAX: +61 (2) 9717 3606
Mobile: 0417 017 503
E-mail: robert.robinson at ansto.gov.au
www.ansto.gov.au/ansto/bragg/index.html
www.ansto.gov.au/ansto/bragg/staff/s_rob.html
Important: This transmission is intended only for the use of the addressee.
It is confidential and may contain privileged information or copyright
material. If you are not the intended recipient, any use or further
disclosure of this communication is strictly forbidden. If you have received
this transmission in error, please notify me immediately by telephone and
delete all copies of this transmission as well as any attachments.
----------------------------------------------------------------------------
----------------
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://www.neutron.anl.gov/pipermail/neutron/attachments/20061103/6d721939/attachment.htm
More information about the Neutron
mailing list